Work on the aqueduct progressing ‘satisfactorily’

According to the Council, work on restoring the aqueduct is progressing ‘satisfactorily’, with some of the scaffolding already having been removed.

The project was started on August 8th 2010 with a budget of €513,000 and a completion period of 13 months.

The latest show a budget of €537,758 and a completion period of nine months. The project had to be amended after the discovery of previously unknown texts and engravings on the monument.

The project has apparently created 13 jobs.